9. COST ESTIMATES
ITEM
UM (M/E) QUANTITY UNIT COST COST($000)
PRIMARY FACILITY 23,118
21410 Modified TEMF, Large - Army, Reg m2 (SF) 4,245 ( 45,694) 3,114 (13,217)
44220 ALT Gen Purp (GP) Warehouse, Hi- m2 (SF) 2,475 ( 26,642) 1,667 (4,125)
44220 ADD Gen Purp (GP) Warehouse, Hi- m2 (SF) 399.48 ( 4,300) 1,066 (426)
85110 Military Equipment Parking m2 (SY) 135,160 ( 161,650) 32.08 (4,336)
00000 Cyber Security Measures LS -- -- (750)
Sustainability/Energy Measures LS -- -- (264)
SUPPORTING FACILITIES 9,319
Electric Service LS -- -- (863)
Water, Sewer, Gas LS -- -- (1,524)
Paving, Walks, Curbs And Gutters LS -- -- (1,112)
Storm Drainage LS -- -- (288)
Site Imp(4,531) Demo( ) LS -- -- (4,531)
Information Systems LS -- -- (295)
Antiterrorism Measures LS -- -- (103)
Other LS -- -- (603)
ESTIMATED CONTRACT COST 32,437
CONTINGENCY (5.00%) 1,622
SUBTOTAL 34,059
SUPV, INSP & OVERHEAD (5.70%) 1,941
TOTAL REQUEST 36,000
TOTAL REQUEST (ROUNDED) 36,000
TOTAL RELATED FURNITURE & EQUIP (4,836)
10. Description of Proposed Construction Construct an Equipment Concentration Site (ECS)
consisting of a 45,694 square feet (SF) Tactical Equipment Maintenance Facility (TEMF),
alteration of a 26,642 SF Organizational Storage Building, addition of a 4,300 SF
Organizational Storage Building, and 161,650 square yard Military Equipment Parking (MEP)
(gravel / concrete) all collocated in the vicinity of Gainesville, Florida. Building
design(s) will comply with Unified Facilities Criteria, UFC 4-171-05, Army Reserve
Facilities. Supporting facilities include land clearing, paving, aprons, fencing, wash
rack/platform(s), bi-level equipment loading ramps, general site improvements, and
utility connections. Accessibility for the disabled will be provided. Anti Terrorism
Force Protection (ATFP) and physical security measures will be incorporated into the
design including maximum standoff distances from roads, parking areas and vehicle
unloading areas. Cyber Security Measures will be incorporated into this project.
Sustainability/Energy measures will be provided. Facilities will be designed to a minimum
life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02)
including energy efficiencies, building envelope and integrated building systems
performance. Air Conditioning (Estimated 397 kWr/113 Tons).
11. REQ: 7,120 m2 ADQT: NONE SUBSTD: NONE
PROJECT: To provide an Equipment Concentration Site (ECS) consisting of a 45,694 SF
Tactical Equipment Maintenance Facility (TEMF), alteration of a 26,642 SF Organizational
Storage Building, addition of a 4,300 SF Organizational Storage Building, and 161,650 SY
of Military Equipment Parking (MEP) (gravel / concrete) in the vicinity of Gainesville,
1. COMPONENT 2. DATE
AR
FY 2021 MILITARY CONSTRUCTION PROJECT DATA
February 2020
3. INSTALLATION AND LOCATION 4. PROJECT TITLE
Gainesville
Florida ECS TEMF / Warehouse
5. PROGRAM ELEMENT 6. CATEGORY CODE 7. PROJECT NUMBER 8. PROJECT COST ($000)
0532292A 21410 CAR 21-82197
Auth 36,000
Approp 36,000
PAGE NO. 2 PREVIOUS EDITION IS OBSOLETE DD FORM 1391, JUL 1999