PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 1 of 18 R-1 Line #90
Exhibit R-2, RDT&E Budget Item Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600: Research, Development, Test & Evaluation, Air Force / BA 5: System
Development & Demonstration (SDD)
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance Development
COST ($ in Millions)
Prior
Years FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total FY 2022 FY 2023 FY 2024 FY 2025
Cost To
Complete
Total
Cost
Total Program Element
- 44.788 28.043 23.076 0.000 23.076 9.183 6.705 6.825 6.950 Continuing Continuing
653133: Bombs & Fuzes
- 39.742 19.054 18.011 0.000 18.011 4.010 1.440 1.466 1.492 Continuing Continuing
655361: Stores-Aircraft Interface
- 5.046 8.989 5.065 0.000 5.065 5.173 5.265 5.359 5.458 Continuing Continuing
A. Mission Description and Budget Item Justification
The Armament Ordnance Development program provides for the initial and continuing development of weapons, munitions, and munitions equipment for aircraft
integration, support, and operational use. This program develops, characterizes, and improves current, future, and legacy munitions, ammunitions, and subsystems.
653133: The Bombs & Fuzes project improves conventional weapons/munitions (kinetic and non-kinetic), fuzes, and height-of-burst sensors (HOBS), and develops and
integrates complementary position, navigation, and timing (PNT) capabilities (i.e. GPS, non-GPS, optical, passive, active, etc.). This project also provides an opportunity
to quickly insert emerging technologies into existing and developing aircraft munitions and fuzes. Bombs & Fuzes provides research, development, and testing of
conventional warheads, fuzing, HOBS modifications, and anti-personnel anti-materiel (APAM) weapons to improve lethality against area, mobile, hard and deeply buried,
and fixed targets. This project provides for the development and testing necessary to provide a suitable manufacturing base of conventional warheads, fuzes, HOBS,
and munitions materiel handling equipment (MMHE).
655361: The Stores-Aircraft Interface project is home to the Universal Armament Interface (UAI). UAI is the Air Force's common standard aircraft/weapon interface
and is an acquisition requirement, to be used by all weapons and combat aircraft as practicable. The UAI program continues development and maintenance of the
standardized interface including mission planning components. Users include Army and Navy customers. The UAI program office is also responsible for development,
enhancement, and maintenance of the standard to support coalition, allied, and joint interoperability efforts for weapons-platform interface. These responsibilities include
acquisition, upgrade, repair and provision of UAI certification tools, and implementation support to US Air Force, Army, Navy and allied aircraft and weapons systems.
UAI provides cost/schedule savings over traditional integration efforts. This is accomplished by enabling integration of weapons independent of aircraft Operational Flight
Programs (OFP) cycles.
This program element may include necessary civilian pay expenses required to manage, execute, and deliver Armament/Ordnance Development weapon system
capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in Program Elements 0605831F.
This program is in Budget Activity 5, System Development and Demonstration (SDD) because it has passed Milestone B approval and is conducting engineering and
manufacturing development tasks aimed at meeting validated requirements prior to full rate production.
Volume 2 - 603
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 2 of 18 R-1 Line #90
Exhibit R-2, RDT&E Budget Item Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600: Research, Development, Test & Evaluation, Air Force / BA 5: System
Development & Demonstration (SDD)
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance Development
B. Program Change Summary ($ in Millions)
FY 2019 FY 2020 FY 2021 Base FY 2021 OCO FY 2021 Total
Previous President's Budget 49.590 28.043 6.197 0.000 6.197
Current President's Budget 44.788 28.043 23.076 0.000 23.076
Total Adjustments -4.802 0.000 16.879 0.000 16.879
• Congressional General Reductions 0.000 0.000
• Congressional Directed Reductions 0.000 0.000
• Congressional Rescissions 0.000 0.000
• Congressional Adds 0.000 0.000
• Congressional Directed Transfers 0.000 0.000
• Reprogrammings -3.260 0.000
• SBIR/STTR Transfer -1.542 0.000
• Other Adjustments 0.000 0.000 16.879 0.000 16.879
Change Summary Explanation
FY19: Reprogrammings of -$8M and +$4.740 were accomplished to balance resource requirements among the Cockpit-selectable Height of Burst Sensor (C-
HOBS), M-Code, and the Advanced Medium Range Air-to-Air Missile (AMRAAM) programs.
FY21: AF provided C-HOBS $21M to complete Engineering and Manufacturing Development.
The FY 2021 Armament/Ordnance funding request was reduced by $4.1M to account for the availability of prior year execution balances.
Volume 2 - 604
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 3 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
COST ($ in Millions)
Prior
Years FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total FY 2022 FY 2023 FY 2024 FY 2025
Cost To
Complete
Total
Cost
653133: Bombs & Fuzes
- 39.742 19.054 18.011 0.000 18.011 4.010 1.440 1.466 1.492 Continuing Continuing
Quantity of RDT&E Articles - - - - - - - - - -
A. Mission Description and Budget Item Justification
The Bombs & Fuzes project improves conventional weapons/munitions (kinetic and non-kinetic), fuzes, and height-of-burst sensors (HOBS), and develops and
integrates complementary position, navigation, and timing (PNT) capabilities (i.e. GPS, non-GPS, optical, passive, active, etc.). This project also provides an opportunity
to quickly insert emerging technologies into existing and developing aircraft munitions and fuzes. Bombs & Fuzes provides research, development, and testing of
conventional warheads, fuzing, HOBS modifications, and anti-personnel anti-materiel (APAM) weapons to improve lethality against area, mobile, hard and deeply buried,
and fixed targets. This project provides for the development and testing necessary to provide a suitable manufacturing base of conventional warheads, fuzes, HOBS,
and munitions materiel handling equipment (MMHE).
- Munitions Materiel Handling Equipment (MMHE): MMHE is a continuing project to develop and improve the standardization and commonality of munitions handling and
armament equipment to preclude duplication. Efforts are primarily the study, design, and development of MMHE and armament control systems; however, support may
be provided to other functional areas as requested. Procurement will be performed and funded by the applicable weapons system project.
- Medium Caliber Ammunition project assesses, refines, and develops medium caliber ammunition, to include, but not limited to, conducting 25mm (F-35) qualification
testing, comparative testing, and mitigating ammunition inventory health issues.
- Insensitive Munitions (IM) project supports AF IM strategic planning to achieve IM compliance IAW U.S. Code, Title 10, Subtitle A, Part N, Chapter 141, Section
2389, ensuring safety regarding insensitive munitions. Models and validates munition performance, integrates less sensitive explosive fills, addresses IM explosive fill
deficiencies, and develops bomb case modifications to improve the response of conventional weapons to unplanned stimuli. This project explores and develops IM
solutions.
- Next Generation Area Attack Weapons (NGAAWs) are a family of unitary area attack weapon capabilities to meet the DoD policy regarding cluster munitions and
unintended harm to civilians. They consist of BLU-134/B and BLU-136/B warheads with a height of burst sensor. BLU-134/B Improved Lethality Warhead (ILW),
NGAAW Increment I, is a near-term solution for area attack as an anti-personnel anti-materiel (APAM) weapon that improves lethality using a 500 lb warhead design and
any variants. The BLU-136/B NGAAW Increment II continues development to provide significantly increased capability and lethality against area targets as an APAM
weapon. This effort is being executed using an accelerated acquisition strategy to study, design, develop, and test a 2,000 lb unitary warhead design and any variants
based on target sets.
- DSU-43/B Cockpit-selectable Height-Of-Burst Sensor (C-HOBS): The C-HOBS will be a replacement for the current DSU-33D/B proximity sensor. C-HOBS will replace
the single factory height-of-burst setting with the addition of multiple height-of-burst options selectable via both manual switches and a cockpit interface. These selection
Volume 2 - 605
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 4 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
options allow flexibility during flight to address a wide array of targets. The C-HOBS is intended to interface with Combat Air Forces (CAF) aircraft and provide proximity
height-of-burst functionality to general and special purpose weapons (to include NGAAWs).
- Joint Air-to-Ground Missile for Fixed Wing Aircraft (JAGM-F) is an improvement to the Army-led JAGM, which will allow the missile to be ejected from fixed wing aircraft
in order to eliminate time sensitive moving targets and high value covered/sheltered targets. JAGM-F will be able to combat adverse weather/low visibility battlefield
and countermeasure environments as well as austere communication environments. JAGM-F will have the ability to engage multiple target types near-simultaneously
in multiple engagement modes. Efforts include but are not limited to capability demonstration design, testing, and qualification, and manufacture/build components to
production standards. Intent is to investigate meeting all BRU-55, BRU-70, and BRU-61 environments.
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Title: Munitions Materiel Handling Equipment (MMHE)
Description: Armament Standardization/Control/Munitions Materiel Handling Equipment (MMHE) is a
continuing project to develop and improve the standardization and commonality of munitions handling and
armament equipment to preclude duplication. Efforts are primarily the study, design, and development of MMHE
and armament control systems; however, support may be provided to other functional areas as requested.
Procurement will be performed and funded by the applicable weapons system project.
FY 2020 Plans:
Continue MMHE support projects to include engineering, drafting, proof load, technical data, and safety
authorizations. Fabricate prototypes for test and evaluation purposes. Continue first article equipment
fabrications for drafting verification and delivery to Air Force units for additional test and evaluation. Provide
support to all system program offices with new weapons and aircraft configurations, as needed. Continue
support to the F-35 with designs and manufacturing of equipment to aid safe munitions loading and
handling of various pylons and adapters. Continue to support the B-21 program office with evaluations
and recommendations for equipment to aid safe munitions loading and handling of various pylons and
adapters. Continue support to the Defense Advanced Research Projects Agency (DARPA) with designs and
manufacturing of equipment to aid safe munitions loading and handling of hypersonic weapons. Continue
support for Air Force Research Laboratory on future munition concept demonstrators. Continue support and
sustainment engineering of all previously existing items developed by the MMHE program office. Continue to
provide MMHE Sustainment office at Robins AFB, GA, with engineering support.
FY 2021 Base Plans:
Continue MMHE support projects to include engineering, drafting, proof load, technical data, and safety
authorizations. Fabricate prototypes for test and evaluation purposes. Continue first article equipment
fabrications for drafting verification and delivery to Air Force units for additional test and evaluation. Provide
0.667 0.714 0.722 - 0.722
Volume 2 - 606
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 5 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
support to all system program offices with new weapons and aircraft configurations, as needed. Continue
support to the F-35 with designs and manufacturing of equipment to aid safe munitions loading and
handling of various pylons and adapters. Continue to support the B-21 program office with evaluations and
recommendations for equipment to aid safe munitions loading and handling of various pylons and adapters.
Continue support to DARPA with designs and manufacturing of equipment to aid safe munitions loading and
handling of hypersonic weapons. Continue support for Air Force Research Laboratory on future munition
concept demonstrators. Continue support and sustainment engineering of all previously existing items
developed by the MMHE program office. Continue to provide MMHE Sustainment office at Robins AFB, GA,
with engineering support.
FY 2020 to FY 2021 Increase/Decrease Statement:
Funding increase is minimal.
Title: Medium Caliber Ammunition
Description: The Medium Caliber Ammunition efforts support the warfighter's medium caliber ammunition
research, development, test, and evaluation (RDT&E) requirements, DoN/USAF collaboration for the medium
caliber family of ammunition, foreign comparative testing, inventory health challenges, procurement of
ammunition, and other emerging technologies.
FY 2020 Plans:
Continue to provide engineering and technical support for PGU-48/B rounds as well as further comparative
testing/EMD of alternative products/sources. Initiate development of the 30mm replacement round. Assess and
mitigate Medium Caliber ammunition inventory health challenges.
FY 2021 Base Plans:
Continue to provide engineering and technical support for PGU-48/B rounds as well as further comparative
testing/EMD of alternative products/sources. Initiate development of the 30mm replacement round. Assess and
mitigate Medium Caliber ammunition inventory health challenges.
FY 2020 to FY 2021 Increase/Decrease Statement:
N/A
0.100 0.100 0.100 - 0.100
Title: Insensitive Munitions (IM) and Emerging Technology
Description: Model and validate current and Emerging Energetics munition performance; assess and correct
IM deficiencies; explore and develop new IM and Energetics technology; conduct strategic IM and Emerging
0.300 0.300 0.300 - 0.300
Volume 2 - 607
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 6 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Energetics planning for the AF; support Joint Service IM efforts; provide technical guidance and test expertise to
AF IM and Emerging Energetics programs.
FY 2020 Plans:
Execute the Insensitive Munitions Strategic Plan (IMSP) and Plan of Action and Milestones (POAM). Begin
Phase II of the Liner project for the BLU-117 which includes engineering passive venting using IM features.
Once features are implemented, qualification testing will take place.
FY 2021 Base Plans:
Execute the Insensitive Munitions Strategic Plan (IMSP) and Plan of Action and Milestones (POAM). Continue
Phase II of the Liner project for the BLU-117 which includes engineering passive venting using IM features.
Once features are implemented, qualification testing will take place.
FY 2020 to FY 2021 Increase/Decrease Statement:
N/A
Title: BLU-136/B Next Generation Area Attack Weapon Increment II
Description: The Next Generation Area Attack Weapon Increment II (NGAAW II) continues development of anti-
personnel anti-materiel (APAM) weapons to improve lethality against area targets via an accelerated acquisition
strategy. This effort studies, designs, develops, and tests a warhead design and any variants which significantly
improve lethality against APAM while meeting current DoD policy on cluster munitions and unintended harm to
civilians.
FY 2020 Plans:
N/A
FY 2021 Base Plans:
N/A
FY 2020 to FY 2021 Increase/Decrease Statement:
N/A
2.819 0.000 0.000 - 0.000
Title: Cockpit-Selectable Height-Of-Burst Sensor (C-HOBS)
Description: DSU-43/B Cockpit-selectable Height-Of-Burst Sensor (C-HOBS). The C-HOBS will be a
replacement for the legacy DSU-33D/B proximity sensor. C-HOBS will replace the single factory height-of-burst
setting with the addition of multiple height-of-burst options selectable via both manual switches and a cockpit
14.362 1.761 16.889 - 16.889
Volume 2 - 608
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 7 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
interface. These selection options allow flexibility during flight to address a wide array of targets. The C-HOBS
is intended to interface with the weapon via the cockpit and provide a cockpit-selectable proximity function for
general and special purpose weapons (to include NGAAWs).
FY 2020 Plans:
Continue to mature development; design and qualification tests; and integration work. Conduct government/
industry reviews working towards completion of Milestone C efforts. Evaluate production representative articles
and complete Initial Product Baseline and Product Support Plan. Complete a CDR Assessment based on test
results for the Milestone Decision Authority (MDA) in preparation of a LRIP Production Decision with a Full Rate
Production Decision in FY21.
FY 2021 Base Plans:
Complete design and qualification tests; and integration work. Conduct government/industry reviews working
towards completion of Milestone C efforts. Start LRIP and First Article Acceptance Testing with a Full-Rate
Production Decision. Pending MDA approval of FRP, will start full-rate production.
FY 2020 to FY 2021 Increase/Decrease Statement:
Funding increased due to added AF funding to complete C-HOBS Engineering and Manufacturing Development.
Title: M-Code Reciever Development
Description: Description: M-Code/EAJ receivers provide an enhanced anti-jam capability. M-Code/EAJ
receivers provide the capability to operate in increasing adversarial A2/AD jamming environment. M-Code/EAJ
receivers also provide increased accuracy, better signal acquisition, and advanced security.
FY 2020 Plans:
N/A
FY 2021 Base Plans:
N/A
FY 2020 to FY 2021 Increase/Decrease Statement:
N/A
4.469 0.000 0.000 - 0.000
Title: Joint Air-to-Ground Missile for Fixed Wing (JAGM-F)
Description: Joint Air-to-Ground Missile for Fixed Wing Aircraft (JAGM-F) is an improvement to the Army-
led JAGM, which will allow the missile to be ejected from fixed wing aircraft in order to eliminate time sensitive
17.025 16.179 0.000 - 0.000
Volume 2 - 609
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 8 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
moving targets and high value covered/sheltered targets. JAGM-F will be able to combat adverse weather/low
visibility battlefield and countermeasure environments as well as austere communication environments. JAGM-
F will have the ability to engage multiple targets types near-simultaneously in multiple engagement modes.
Efforts include but are not limited to capability demonstration design, testing, and qualification, and manufacture/
build components to production standards. Intent is to investigate meeting all BRU-55, BRU-70, and BRU-61
environments.
FY 2020 Plans:
Continue to model the design and build, Jettison and Capture Analysis, Mechanical Design, Electronic Design
and Testing, Electrical Packaging, software design and code development, weapons system integration,
aircraft systems integration, test vehicle design and build, and test vehicle flight planning. Purchase additional
government furnished equipment (GFE) and flight test support.
FY 2021 Base Plans:
N/A
FY 2020 to FY 2021 Increase/Decrease Statement:
Funding decreased due to evolving USAF requirements.
Accomplishments/Planned Programs Subtotals
39.742 19.054 18.011 - 18.011
C. Other Program Funding Summary ($ in Millions)
Line Item FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total FY 2022 FY 2023 FY 2024 FY 2025
Cost To
Complete Total Cost
• PAAF 01 Line Item 353020:
General Purpose Bombs
811.170 631.194 0.000 369.566 369.566 394.673 692.700 414.356 370.988 Continuing Continuing
• PAAF 01 Line Item 356120: Fuzes 180.272 154.214 40.983 107.855 148.838 223.309 188.781 105.411 142.917 Continuing Continuing
• PAAF 01 Line Item
352010: Cartridges
188.227 193.091 123.365 40.434 163.799 161.666 145.812 109.608 122.330 Continuing Continuing
Remarks
N/A
D. Acquisition Strategy
- Fuzes (including C-HOBS) is a continuing effort with most activities performed through contracted services.
Volume 2 - 610
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 9 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
- Munitions Materiel Handling Equipment (MMHE) project activities are performed in-house with limited technical and analysis contract support.
- Medium Caliber Ammunition project activities are performed in-house with technical and analysis contract support, organic government test support, and possible
contracted services (small contracts).
- Insensitive Munitions project activities are performed in-house with limited technical and analysis contract support.
- The BLU-136/B NGAAW Inc II warhead design program will implement an accelerated acquisition program strategy. This strategy includes rapid development and
prototyping of a warhead design resulting in a final, validated Technical Data Package (TDP). The TDP will be used to compete for initial production and follow on
procurement to meet the warfighter requirement. The NGAAW program will continue to evaluate product improvements.
- Joint Air-to-Ground Missile for Fixed Wing Aircraft (JAGM-F) utilizes the Defense Ordnance Technology Consortium (DOTC) contract combined with modeling and
simulation contract support and government test support.
Volume 2 - 611
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 10 of 18 R-1 Line #90
Exhibit R-3, RDT&E Project Cost Analysis: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
Product Development ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost Category Item
Contract
Method
& Type
Performing
Activity & Location
Prior
Years Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Cost To
Complete
Total
Cost
Target
Value of
Contract
Product Development C/CPAF Not specified. : TBD - - - - - - Continuing Continuing -
IM Various Various : TBD - 0.300 Mar 2019 0.300 Mar 2020 0.300 Mar 2021 - 0.300 Continuing Continuing -
MMHE - Prototypes Various
Prototype Fabrication
Shop : Eglin AFB, FL
- 0.198 Apr 2019 0.134 Apr 2020 0.172 Apr 2021 - 0.172 Continuing Continuing -
BLU-136 NGAAW Concept
Development
Various
Various : Eglin AFB,
FL
- 2.819 - - - - Continuing Continuing -
CHOBS - HW/SW C/Various
Various : Eglin AFB,
FL
- 13.112 Mar 2020 0.000 Jan 2020 6.574 Oct 2020 - 6.574 Continuing Continuing -
JAGM-F C/FFP
DOTC : Huntsville,
AL
- 16.202 Jun 2019 10.668 Mar 2020 - - - Continuing Continuing -
M-Code Receiver
Development
Various
Boeing: : St. Louis,
MO
- 4.469 May 2019 - - - - Continuing Continuing -
Subtotal
- 37.100 11.102 7.046 - 7.046 Continuing Continuing N/A
Remarks
NGAAW concept development continues.
Support ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost Category Item
Contract
Method
& Type
Performing
Activity & Location
Prior
Years Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Cost To
Complete
Total
Cost
Target
Value of
Contract
Support C/CPAF Not specified. : TBD - - - - - - Continuing Continuing -
MMHE - Shipping/Supplies Various
MMHE Program
Office : Eglin AFB,
FL
- 0.019 Mar 2019 0.130 Mar 2020 0.100 Mar 2021 - 0.100 Continuing Continuing -
JAGM-F - Test Vehicles Various Army : Huntsville, AL - 0.000 0.880 Jun 2020 - - - Continuing Continuing -
Subtotal
- 0.019 1.010 0.100 - 0.100 Continuing Continuing N/A
Volume 2 - 612
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 11 of 18 R-1 Line #90
Exhibit R-3, RDT&E Project Cost Analysis: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
Test and Evaluation ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost Category Item
Contract
Method
& Type
Performing
Activity & Location
Prior
Years Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Cost To
Complete
Total
Cost
Target
Value of
Contract
Test and Evaluation C/CPAF Not specified. : TBD - - - - - - Continuing Continuing -
BLU-136 ILW - Test and
Evaluation
PO Various : Various - - - - - - Continuing Continuing 6.530
CHOBS - Test and
Evaluation
C/Various Various : Various - 0.915 May 2020 1.555 Aug 2020 9.680 Oct 2020 - 9.680 Continuing Continuing -
MMHE - Test Support PO
96 TW : Eglin AFB,
FL
- 0.020 Apr 2019 0.050 Nov 2019 0.050 Nov 2020 - 0.050 Continuing Continuing -
JAGM-F - Test Support Various Various : Various - 0.101 Nov 2019 3.878 Oct 2020 - - - Continuing Continuing -
Subtotal
- 1.036 5.483 9.730 - 9.730 Continuing Continuing N/A
Management Services ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost Category Item
Contract
Method
& Type
Performing
Activity & Location
Prior
Years Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Cost To
Complete
Total
Cost
Target
Value of
Contract
Management Services C/CPAF Not specified. : TBD - - - - - - Continuing Continuing -
Medium Caliber - PMA Various
Various : Eglin AFB,
FL
- 0.100 Jun 2019 0.100 Jun 2020 0.100 Jun 2021 - 0.100 Continuing Continuing -
MMHE - PMA Various
Various : Eglin AFB,
FL
- 0.430 Jun 2019 0.400 Jun 2020 0.400 Jun 2021 - 0.400 Continuing Continuing -
BLU-136/B - PMA Various Various : NV - - - - - - Continuing Continuing -
CHOBS - PMA Various
Various : Eglin AFB,
FL
- 0.335 Oct 2018 0.206 Oct 2019 0.635 Oct 2020 - 0.635 Continuing Continuing -
JAGM-F - PMA Various
Various : Eglin AFB,
FL
- 0.722 Sep 2019 0.753 Aug 2020 - - - Continuing Continuing -
Subtotal
- 1.587 1.459 1.135 - 1.135 Continuing Continuing N/A
Prior
Years FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost To
Complete
Total
Cost
Target
Value of
Contract
Project Cost Totals
- 39.742 19.054 18.011 - 18.011 Continuing Continuing N/A
Remarks
Volume 2 - 613
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 12 of 18 R-1 Line #90
Exhibit R-4, RDT&E Schedule Profile: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 FY 2025
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Bombs and Fuzes
MMHE: design, prototype, test priority efforts
Execute IMSP POAM
BLU-136/B: Warhead design/initial prototype
C-HOBS: RFP/Source selection
C-HOBS: Contract Award
C-HOBS: Design, build, test, and integrate
Medium Caliber Ammunition: Assess, refine,
and develop
JAGM-F contract award
JAGM-F: Conduct demononstration
M-Code Receivers Development
Volume 2 - 614
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 13 of 18 R-1 Line #90
Exhibit R-4A, RDT&E Schedule Details: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
653133 / Bombs & Fuzes
Schedule Details
Start End
Events by Sub Project Quarter Year Quarter Year
Bombs and Fuzes
MMHE: design, prototype, test priority efforts 1 2019 4 2025
Execute IMSP POAM 1 2019 4 2025
BLU-136/B: Warhead design/initial prototype 1 2019 4 2019
C-HOBS: RFP/Source selection 1 2019 2 2019
C-HOBS: Contract Award 2 2019 2 2019
C-HOBS: Design, build, test, and integrate 2 2019 4 2021
Medium Caliber Ammunition: Assess, refine, and develop 1 2019 4 2025
JAGM-F contract award 3 2019 3 2019
JAGM-F: Conduct demononstration 3 2019 4 2021
M-Code Receivers Development 3 2019 4 2020
Volume 2 - 615
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 14 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
655361 / Stores-Aircraft Interface
COST ($ in Millions)
Prior
Years FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total FY 2022 FY 2023 FY 2024 FY 2025
Cost To
Complete
Total
Cost
655361: Stores-Aircraft Interface
- 5.046 8.989 5.065 0.000 5.065 5.173 5.265 5.359 5.458 Continuing Continuing
Quantity of RDT&E Articles - - - - - - - - - -
A. Mission Description and Budget Item Justification
655361: The Stores-Aircraft Interface conducts stores-aircraft interface upgrades and standards development to include the Universal Armament Interface (UAI). UAI is
an Air Force initiative to develop standardized software interfaces in aircraft weapons and mission planning. The savings realized from this effort is on average 6 years
of schedule and $22M per aircraft/weapon combination. This is accomplished by enabling integration of weapons independent of aircraft Operational Flight Programs
(OFP) cycles. UAI is currently implemented on the F-15E, F-16 Block 40/50 and European Participating Air Forces (EPAF) F-16 aircraft, Small Diameter Bomb (SDB) I
and II, Joint Direct Attack Munition (JDAM), Laser JDAM, Joint Air-to-Surface Stand-off Missile (JASSM), and Precision Guided Munitions Planning Software (PGMPS).
Planned implementation include Joint Strike Fighter (JSF/F-35), B-21, MQ-9, JASSM-Extended Range (JASSM-ER), F/A-18, Advanced Anti-Radiation Guided Missile
- Extended Range (AARGM-ER), Combat Weapons Delivery Software (CWDS), SPEAR3, Joint Strike Missile (JSM), and the Turkish Stand Off Missile - Joint (SOM-
J). The UAI program office is responsible for development and enhancement of the standard, support to coalition/allied/joint interoperability efforts for weapons-platform
interface, provision of certification tools, and implementation support to aircraft and weapons.
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Title: Universal Armament Interface (UAI) Development
Description: Continue development and maintenance of the Air Force's mandated aircraft/weapon interface, to
include UAI Mission Planning and Launch Acceptability Region (LAR) components.
FY 2020 Plans:
Evolving requirements force continued development and configuration management of UAI to support the
SAF/AQ UAI mandate. All air-to-ground weapon and aircraft systems now require UAI support in multiple
forms. Support and facilitate certification efforts, working groups, technical meetings, workshops, risk reduction
assessments, common mission planning components, as well as platform- and weapon-specific implementations
of UAI. Maintain and logistically support a fleet of UAI certification tools to meet current and future user system
integration needs. The tools used among aircraft and weapons programs reduce time/cost of UAI integration
efforts and provide a common means to certify a UAI compliant system. Support multinational Memorandum of
Understanding system implementation of UAI including the Joint Strike Missile (JSM), SPEAR 3, and Stand Off
Missile - Joint (SOM-J).
FY 2021 Base Plans:
5.046 8.989 5.065 - 5.065
Volume 2 - 616
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 15 of 18 R-1 Line #90
Exhibit R-2A, RDT&E Project Justification: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
655361 / Stores-Aircraft Interface
B. Accomplishments/Planned Programs ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Continue development and configuration management of UAI in response to evolving requirements to include
expanding capability to support air-to-air weapon integration. Ongoing air-to-ground integration support includes
all USAF weapons, aircraft including USN and US Army customers. Support working groups, technical meetings
and workshops, risk reduction assessments, common mission planning, and platform-specific implementation
of UAI. Maintain and logistically support existing certification tools to meet current and future user system
integration lab test certification needs. These tools are shared among aircraft and weapons programs to reduce
time and cost for UAI integration efforts. Support multinational Memorandum of Understanding including but not
limited to Joint Strike Missile (JSM), SPEAR 3, and Stand Off Missile - Joint (SOM-J).
FY 2020 to FY 2021 Increase/Decrease Statement:
Funding decreased due to a return of funding at a historical level of effort.
Accomplishments/Planned Programs Subtotals
5.046 8.989 5.065 - 5.065
C. Other Program Funding Summary ($ in Millions)
N/A
Remarks
N/A
D. Acquisition Strategy
In December 2004, under the authority of a class Justification and Approval (J&A), the UAI program office awarded individual Cost Plus Fixed Fee (CPFF) contracts to
Boeing, Lockheed Martin, Northrop Grumman, and Raytheon. Each Original Equipment Manufacturer is responsible for a different piece of the total UAI requirement
based on its product-specific (platform/weapon) expertise. During FY10, these contracts expired. Under the authority of the class J&A, Cost Plus Incentive Fee (CPIF)
contracts were awarded to the four UAI vendors in August 2010. Follow-on period of performance was awarded in March 2014 for 16 months to better align future
contract awards with funding through the Future Years Defense Program. The period of performance was extended to 1 November 2015 to allow immediate start of
the effort on F-35/JSF request for changes. A new J&A was approved in January 2015 for the follow-on sole source contracts to the original equipment manufacturers.
These new sole-source contracts were awarded in November 2015 and expired in November 2019. A new J&A was signed in December 2018 and four new five-year
sole source contracts (CPFF) were awarded in November 2019.
Volume 2 - 617
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 16 of 18 R-1 Line #90
Exhibit R-3, RDT&E Project Cost Analysis: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
655361 / Stores-Aircraft Interface
Product Development ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost Category Item
Contract
Method
& Type
Performing
Activity & Location
Prior
Years Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Cost To
Complete
Total
Cost
Target
Value of
Contract
Interface Control
Document (ICD)
Development/Updates/
Maintenance
SS/
Various
Boeing Northrop
Grumman Lockheed
Martin Raytheon :
Various
- 4.846 Nov 2018 8.787 Nov 2019 4.861 Nov 2020 - 4.861 Continuing Continuing -
Certification Tool SS/CPFF
Boeing Northrop
Grumman Lockheed
Martin Raytheon :
Various
- - - - - - Continuing Continuing -
Subtotal
- 4.846 8.787 4.861 - 4.861 Continuing Continuing N/A
Remarks
New 5 year Follow-on contract will be awarded in November 2019.
Management Services ($ in Millions)
FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost Category Item
Contract
Method
& Type
Performing
Activity & Location
Prior
Years Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Award
Date Cost
Cost To
Complete
Total
Cost
Target
Value of
Contract
A&AS Contractor Support Various Various : Various - 0.140 0.142 0.144 - 0.144 Continuing Continuing -
Program Office Travel C/CPAF Not specified. : TBD - 0.060 0.060 0.060 - 0.060 Continuing Continuing -
Subtotal
- 0.200 0.202 0.204 - 0.204 Continuing Continuing N/A
Remarks
PE Systems Contractor provides support to the Program Office for financial services.
Prior
Years FY 2019 FY 2020
FY 2021
Base
FY 2021
OCO
FY 2021
Total
Cost To
Complete
Total
Cost
Target
Value of
Contract
Project Cost Totals
- 5.046 8.989 5.065 - 5.065 Continuing Continuing N/A
Remarks
Volume 2 - 618
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 17 of 18 R-1 Line #90
Exhibit R-4, RDT&E Schedule Profile: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
655361 / Stores-Aircraft Interface
FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 FY 2025
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Stores-Aircraft Interface
Governance (Super Joint Interface Control
Working Group)
Certification Tools (CTs) Dev / Update
UAI (Msn Plng) Common Component
WPN Sustainment/Regression Efforts: JDAM,
JASSM-ER, SDB I+II
A/C Sustainment/Regression Efforts: F-16 Blk
40/50, F-15E
WPN Dev: SiAW, JSM, SPEAR3, LRASM,
AARGM-ER, JAGM-F, Golden Horde
A/C Dev: F-16 Foreign Military Sales, F-35,
B-21, B-1, A-10, F-22, F-18, MQ-9, F-15EX,
MQ-IC
Volume 2 - 619
UNCLASSIFIED
PE 0604602F: Armament/Ordnance Development
UNCLASSIFIED
Air Force Page 18 of 18 R-1 Line #90
Exhibit R-4A, RDT&E Schedule Details: PB2021Air Force
Date: February 2020
Appropriation/Budget Activity
3600 / 5
R-1 Program Element (Number/Name)
PE 0604602F / Armament/Ordnance
Development
Project (Number/Name)
655361 / Stores-Aircraft Interface
Schedule Details
Start End
Events by Sub Project Quarter Year Quarter Year
Stores-Aircraft Interface
Governance (Super Joint Interface Control Working Group) 1 2019 4 2025
Certification Tools (CTs) Dev / Update 1 2019 4 2025
UAI (Msn Plng) Common Component 1 2019 4 2025
WPN Sustainment/Regression Efforts: JDAM, JASSM-ER, SDB I+II 1 2019 4 2025
A/C Sustainment/Regression Efforts: F-16 Blk 40/50, F-15E 1 2019 4 2025
WPN Dev: SiAW, JSM, SPEAR3, LRASM, AARGM-ER, JAGM-F, Golden Horde 1 2019 4 2025
A/C Dev: F-16 Foreign Military Sales, F-35, B-21, B-1, A-10, F-22, F-18, MQ-9,
F-15EX, MQ-IC
1 2019 4 2025
Volume 2 - 620